Shut down fresh water generator
Assessed in EN-4231 Sea Term IV: Marine Engineering
Condition
Using an approved simulator, in the laboratory, or aboard ship and given access to a fresh water generator.
Performance Requirements
Behavior | Standard |
---|---|
The student will: | During assessment, the student shall, at a minimum: |
Identify the valves and pumps associated with the freshwater generator |
Identify:
|
Line up distillate discharge to the bilge | |
Secure the freshwater generator |
Follow the ship specific evaporator securing procedure provided during training |
Supports Table A-III/1 officers in charge of an engineering watch
Competence | Knowledge, Understanding & Proficiency | Task |
---|---|---|
Operate main and auxiliary machinery and associated control systems |
A4.1 Basic construction and operation principles of machinery systems, including:
|
Shut down fresh water generator |