Assessment OICEW-8-2D
Inspect valve manifold
Assessed in EN-2231 Sea Term II: Marine Engineering
Condition
Aboard ship or in workshop, given a piping diagram and other equipment needed to complete the task.
Performance Requirements
Behavior | Standard |
---|---|
The student will: | During assessment, the student shall, at a minimum: |
Lockout/tagout valve manifold |
Identify contents of pipe Isolate pipe section Relieve pressure and drain section |
Use tools to open up piping for inspection |
Use:
|
Dismantle flanges Inspect interior of pipe Clean and prepare joints for reassembly | |
Use tools and proper joint materials to close up piping system |
Use:
|
Test system to identify leaks |
Perform hydrostatic test for leakage Prove joint leak free |
Supports Table A-III/1 officers in charge of an engineering watch
Competence | Knowledge, Understanding & Proficiency | Task |
---|---|---|
Maintenance and repair of shipboard machinery and equipment |
C2.3 Maintenance and repair, such as dismantling, adjustment and reassembling of machinery and equipment |
Inspect valve manifold |