Condition
Aboard ship, or in an approved simulator, given the engineering log book, the pertinent standing orders, the oil record book, and proper safety equipment.
Performance requirement
Behavior | Standard |
---|---|
The student will: | During assessment, the student shall, at a minimum: |
Plan a bilge pumping operation |
Identify space to be pumped Identify location to receive bilges Select bilge pump to be used Insure sufficient room in slop tank, if used |
Comply with all applicable regulations Prime bilge pump if necessary | |
Operate the bilge pump or ows |
Monitor:
Maintain strainers as necessary |
Secure the bilge pump when pumping operation is complete |
Secure the bilge pump Secure the bilge manifold |
Make appropriate entries in the Oil Record Book |
|
Location
Assessed in EN‑2231 Sea Term II: Marine Engineering.
References
- Table A-III/1 OICEW-A5.2
- NVIC 17-14 Task 5.2.A
See the Assessment Guidelines for additional specifications of behavior and standards.