ABE Task 5.1.A
 
		Trace out a piping system
MMA Method
In order to satisfy NVIC 18-14 Task 5.1.A , MMA students must:
- Successfully complete MMA Assessment ABE-5G1A Trace out a piping system
NVIC Method
See NVIC method.
| STCW Competence | Knowledge, Understanding, and Proficiency | 
| Contribute to the operation of equipment and machinery | ABE-A8.1 Safe operation of equipment, including: .1 valves and pumps | 
| Condition | Behavior | Standard | 
|---|
| On a vessel or in a laboratory or workshop, given a piping system, | the candidate demonstrates the ability to trace the system, identify & operate valves, and operate liquid-level measuring devices. 
 
 | The candidate traces out a piping system specified by the assessor and demonstrates or describes: 
Purpose of the system tracedLocation of the valves to be used to normally start and/or shutdown the systemLocation of the valves to be used in the event of an emergency shutdown of the system, including emergency shutdown devicesManual operation of each type of valve in that system, both locally and remotely operatedManual operation of any in-tank measuring devicesProbable location of any leakage, what form that leakage may take, onboard notification procedures, and what precautions should be followedAny topping off procedures that are followedAny stripping procedures that are followed; andProtection of bilge and ballast suctions during normal operations and other configurations where the bilge and ballast suctions and wells may become contaminated. |