OICEW-5-1B
Start refrigeration system
Condition
Using an approved simulator, in the laboratory, or aboard ship and given access to a refrigeration system that has been secured.
Performance requirement
Behavior | Standard |
---|---|
The student will: | During assessment, the student shall, at a minimum: |
Identify the valves and equipment associated with the refrigeration unit |
Identify:
|
Check compressor lubrication |
Verify visible oil level |
Check refrigerant level |
Verify visible receiver level |
Line-up refrigeration unit |
Line up cooling water supply LIne up refrigerant circuit Leave compressor suction valve closed |
Start associated equipment |
Energize box solenoids Start diffuser fans, brine pumps, etc. as required |
Start the refrigeration compressor |
Gradually open compressor suction valve Verify:
|
Operate the refrigeration unit until conditions stabilize |
Monitor:
|
Note: Not all steps are possible on all refrigeration systems.
See the Engineering Assessment Guidelines for additional specifications of behavior and standards.
Note: This assessment supports KUP OICEW-A4.1, and is assessed in EN-3213 Refrigeration.