OICEW-7-1C

Pre-start inspection of steam turbo-generator

Function: Marine engineering at the operational level

Competence Knowledge, Understanding & Proficiency Task

Operate main and auxiliary machinery and associated control systems

A4.1 Basic construction and operation principles of machinery systems, including:

  1. marine diesel engine
  2. marine steam turbine
  3. marine gas turbine
  4. marine boiler
  5. shafting installations, including propeller
  6. other auxiliaries, including various pumps, air compressor, purifier, fresh water generator, heat exchanger, refrigeration, air-conditioning and ventilation systems
  7. steering gear
  8. automatic control systems
  9. fluid flow and characteristics of lubricating oil, fuel oil and cooling systems
  10. deck machinery

Pre-start inspection of steam turbo-generator

Assessed in: EN-3233 Steam and Gas Turbines

Condition

Aboard ship, in the laboratory, or in an approved simulator given access to proper equipment and manufacturer’s technical manual.

Behavior

Plan and conduct a pre-start-up inspection of steam turbo- generator describing actions as they are being performed.

Standard

  1. Plan reflects proper sequence of actions, is complete, and conforms to the requirements of manufacturer’s instructions and ship’s procedures;
  2. Pre- start up inspection of the steam turbo-generator is successful and conducted according to plan;
  3. Actions taken are correctly and completely described;
  4. Required steps taken are verified by assessor utilizing sample checklist as a guide;
  5. No safety violations are observed.